Moving office is one of those jobs that looks logistical until you realise it is mostly an IT project wearing a high-vis jacket. The desks can arrive on a Saturday. The broadband circuit, the phone numbers, the cabling and the Wi-Fi survey do not care about your weekend plans. If you leave the technology to the last week, you are not moving office. You are hoping the office moves itself.

The trap is the box marked IT. Someone puts the routers, the spare cables and a docking station in it, then everyone assumes the box contains a plan. It does not. A box is not an owner, a date or a fallback. Treat the move as a small project with named people and deadlines, and the whole thing gets calmer. Here is the practical version we would use for a UK small business.

Start with dates, not cardboard

Work backwards from the first morning staff need to log in. Call that Switch-On Day. It is not the day the removal van arrives. It is the day people need email, files, phones, printing and Wi-Fi to behave. Everything else is a deadline counting back from that.

Put three names against the plan: someone from the business who can make decisions, someone from IT or your support provider who owns the technical work, and a contact for the building or landlord. If you are the person doing all three, write it down anyway. The plan only works when the dependencies are visible.

Broadband and phones need the longest runway

In the UK, business broadband and leased lines are not next-day purchases. Lead times vary by site and provider, and they can stretch when a new building needs an Openreach survey, wayleave approval or building access. Start the broadband order as early as you can, not after you have signed the lease and started arguing about paint colours.

Phones are their own project. If you are keeping your numbers, porting can take weeks and needs accurate information about the current account. If you are moving to VoIP, check that the new provider can deliver numbers on the right date and that your broadband will be ready to carry calls. Do not cancel the old line until the new one is live and tested. A dead line is a customer service problem wearing a headset.

Ask the landlord the boring questions

Building access is where good plans go to wait in a lobby. Ask who can let engineers into the comms room, what notice they need, whether there is a riser or shared cabinet, and whether any cabling work needs approval. If the building has a managed internet service, find out how your router connects to it and who configures what.

Also ask about power. Specifically, ask whether the server cupboard or comms cabinet has power that stays on, and whether anyone else can switch it off. A cleaner with a vacuum cleaner and a free socket has ended more small-business networks than most cyber attacks.

Cabling: assume nothing, test everything

Old cabling is the quiet trap. The previous tenant swore the ports worked. The letting agent says the cabling is fine. Nobody has plugged a tester into it. Before you rely on it, get the ports labelled and tested. If you are running new cable, get a simple diagram showing which wall port goes to which patch panel port. Future you will be grateful, probably at 5pm on a Friday.

If you are moving a small team, you may not need a full cabling project. You do need a sensible plan for where the router, switch and access points will live. Do not shove the router in a metal cupboard behind a filing cabinet and hope. Wi-Fi is radio, not magic. It hates cupboards, thick walls and being asked to cover a whole floor from one corner.

Wi-Fi, printing and the humble test print

On the day you get access, do a quick Wi-Fi check in the places people will actually work. Not just next to the router. Check the meeting room, the corner desk and the spot where the director likes to take calls. If the signal is weak, move an access point or add one before the furniture arrives. It is much easier to run a cable in an empty room than around a fully assembled team.

Printing deserves its own line because it always gets forgotten. Confirm the printer is on the network, that the right people have drivers, and that scanning to email or SharePoint still works. A test print is not glamorous, but neither is a Monday morning queue around a device that nobody can find on the network.

Cloud files are not automatically sorted by a new postcode

If your files live in Microsoft 365, SharePoint or OneDrive, the move should be easier. That does not mean it needs no checking. Make sure people know how to sign in from the new site, that multi-factor authentication still works on their phones, and that any local drives or old shared folders are either migrated or deliberately retired. Do not move a messy file server to a new office and call it a fresh start.

This is also the moment to check the logins nobody owns: the domain registrar, DNS, the Microsoft 365 tenant, the broadband account and the phone system. If the only person with those details left two years ago, find out now. Forgotten domain and DNS logins are a special kind of pain because they affect email, websites and everything that points at them.

Go-live test before the kettle

Book a proper test day before staff arrive. Power up the router, switch and access points. Test wired and wireless connections. Send and receive email from a phone and a laptop. Make a call to an outside number. Open a cloud file. Print something. Test the meeting room screen. Then write down what failed and who is fixing it.

If possible, have one non-technical person do the test. They will find the things IT has learned to work around without noticing. That is exactly what you want before the rest of the team turns up.

The printable checklist

The box marked IT does not need to be bigger. It needs to be a plan with dates, owners and a test. Do that, and the move can be a bit dull. Dull is exactly what you want from business technology on a Monday morning.

All Articles

Related Articles

The Seats Nobody Sits In: A Pre-Renewal Microsoft 365 Licence Tidy-Up

The Seats Nobody Sits In: A Pre-Renewal Microsoft 365 Licence Tidy-Up

The Contract You Read at Lunchtime: Stress-Testing IT Support Before It Matters

The Contract You Read at Lunchtime: Stress-Testing IT Support Before It Matters

Someone's Leaving on Friday: The 30-Minute Access Shutdown That Saves the Rest of Us

Someone's Leaving on Friday: The 30-Minute Access Shutdown That Saves the Rest of Us